Back to Blog
Construction

Understanding RCC Construction:
A Student's First-Hand Guide

RCC water tank construction — MICADA internship site

Underground RCC water tank under construction — MICADA internship, Mahendragarh, Haryana

When I started my 6-month internship with MICADA (Minor Irrigation & Command Area Development Authority), Haryana Government, I expected to observe. What I didn't expect was to be standing knee-deep in the construction process of a full underground RCC water tank — from the very first stake in the ground to the final surface finish.

This article is my attempt to document everything I witnessed and learned. Not the textbook version — the real version, with dust, concrete, and the kind of problem-solving that only happens on a live site.

What is RCC?

Reinforced Cement Concrete (RCC) is concrete that is strengthened by embedding steel reinforcement bars (rebar) inside it. This combination gives structures both compressive strength (from concrete) and tensile strength (from steel), making it ideal for underground water tanks, foundations, beams, and slabs.

The Full Construction Sequence — Stage by Stage

Here is the complete sequence I observed for the underground RCC water tank at the MICADA site:

STAGE 01
Site Marking
Setting out the tank boundary using survey instruments, pegs, and lime marking on the ground.
STAGE 02
Soil Excavation
Removing soil to the required depth using JCB excavators and manual clearing of corners.
STAGE 03
PCC Laying
Plain Cement Concrete base layer (levelling course) poured and levelled before reinforcement.
STAGE 04
Steel Reinforcement
Rebar placed per design drawings. Binding wire used to tie intersections. Cover blocks placed.
STAGE 05
Formwork / Shuttering
Temporary wooden or steel frames placed to mould the concrete into the required shape.
STAGE 06
RCC Beam Casting
Concrete mix (M20 or M25) poured into the formwork, vibrated to remove air pockets, levelled.
STAGE 07
Curing
Water curing for minimum 28 days. This is critical — I saw jute bags and ponding used on site.
STAGE 08
Finishing & Waterproofing
Internal plastering with waterproofing compound. External backfilling after structure is complete.

What I Learned That No Textbook Tells You

1. Cover Blocks Are Not Optional

In textbooks, "clear cover" is just a number. On site, I watched labourers carefully place small concrete cover blocks under each rebar layer to maintain the design spacing from the formwork. Without them, the rebar can touch the surface, leading to corrosion over time. This one detail directly affects the structure's 50-year life.

2. Concrete Vibration Matters More Than You Think

A needle vibrator was inserted into the concrete every 30–40 cm while pouring. I initially thought it was optional. The site engineer explained that without proper vibration, air bubbles get trapped — creating voids called honeycombing — which severely weakens the structure. Every insertion, every movement mattered.

3. Curing Is The Most Neglected Step

I was surprised to see how much time and effort went into curing. Concrete gains only 30% of its strength in the first 3 days — the remaining 70% comes from proper hydration over 28 days. On the MICADA site, the supervisors were strict about jute bag moisture and water ponding schedules. This discipline is often skipped on private sites, and it's why many structures fail prematurely.

4. The Excavation Depth Tolerance

The excavation was not just "dig until it looks deep enough." The engineers cross-checked the base level using a dumpy level after every major excavation phase. The tolerance was ±25mm. Anything more meant re-excavation or compensating with extra PCC thickness — both costly.

Key Takeaway

The gap between textbook civil engineering and site civil engineering is significant. The theory gives you the framework — but the site teaches you why every detail in that framework exists. If you can, visit even one live RCC construction site before you graduate.

Quality Checks I Observed on Site

  • Slump test for concrete workability before every major pour
  • Cube testing samples prepared and sent to lab (M20/M25 mix)
  • Rebar diameter and spacing cross-checked against structural drawings
  • Level checks at foundation and at each slab before concrete is poured
  • Formwork inspection for leakage before pouring begins

Final Thoughts

Watching the complete lifecycle of an RCC water tank — from a bare patch of soil to a finished underground structure capable of storing thousands of litres of water — was one of the most educational experiences of my engineering journey.

The real lesson wasn't about the concrete mix ratio or the rebar spacing. It was about attention to process. Every stage has a purpose. Skipping or rushing any one of them has consequences that might not show up for years — but when they do, they're expensive and potentially dangerous.

If you're a civil engineering student, make sure you find a way onto a real construction site before you graduate. No amount of lectures or textbooks can replicate what a single day on site teaches you.

More Articles

Mussoorie Survey Camp
Surveying
Mussoorie Survey Camp: What They Don't Teach You in Classrooms
Inside an 8 MLD STP
Water Infra
Inside an 8 MLD Sewage Treatment Plant: A Complete Walkthrough